Newsletter:
Dec 2001/ Issue 1
Improving Nuclear Reactor Safety in Ukraine
Pacific Northwest National
Laboratory (PNNL) recently completed two projects for the
National Nuclear Security Administration (NNSA) that made
significant contributions toward improving nuclear safety
in Ukraine. These were the completion of a full-scope
simulator for the Rivne Nuclear Power Plant (NPP) Unit 3,
and completion of a heat plant for the Chornobyl NPP.
In
May, the NNSA and Ukraine’s nuclear utility, Energoatom,
recognized completion of the full-scope simulator for Rivne
Unit 3. In June, the NNSA and Ukrainian counterparts (the
Ministry of Fuel and Energy and Ukraine Energoatom
(government organizations), Chornobyl NPP, Ukrenergoprom
(Design Institute), Yuzhteploenergomontazh (General
Construction Contractor), and EnergoPromInvest (General
Startup Contractor) completed construction of a heat plant to
be used to facilitate the decommissioning of Chornobyl. Both
projects helped Ukraine meet international nuclear reactor
safety standards thereby reducing the threat of nuclear
accidents and the consequences such an event would have for
neighboring countries and the environment.
At the acceptance ceremony of
Rivne’s Unit 3 simulator, Joe Cleary, manager of the Rivne
project said, “Training on this new simulator will advance
the capabilities of Rivne Unit 3 operators and will lead to
major improvements in the overall safety of the plant.”
Full-scope simulators are complete-size physical replicas of
nuclear plant control rooms, equipped with exact replicas of
the switches, controllers, indicators, and other operational
and safety devices found in reactor control rooms. Each
simulator is designed to replicate a specific plant control
room and is used to train reactor operators and supervisors
to handle both regular and emergency plant operations. The
Rivne simulator was designed for the site’s only
Soviet-designed 950 MWe VVER-1000. The $11.5 million
simulator has been on order and on schedule for installation
and operation since January 1996. GSE Power Systems of
Columbia, Maryland was the prime contractor on the project,
with Russian and Ukrainian sub-contractors participating in
construction and installation of the simulator. Rivne is
scheduled to receive another simulator next year for the
Rivne Unit 2 Reactor, a VVER-440/213.
Completion of the Chornobyl heat
plant facilitates decommissioning of the Chornobyl NPP by
removing reliance on a smaller, “back up” heat plant designed
primarily for emergency heating. The back up plant was
equipped to provide only for critical needs, and had been
used since the December 2000 shutdown of the Unit 3 Reactor.
The new heat plant will keep pipes from freezing and
cracking, preventing leakage of contaminated water, and will
help meet the operational needs of decommissioning facilities
to be built in the near future.
The new heat plant contains all
auxiliary systems necessary for safe and efficient operation.
The newly completed plant consists of three 57 Mwt hot water
boilers and three 40 Mwt steam boilers. It is connected to
the Chornobyl heat network piping and receives electrical
power from the site distribution system. The plant is
primarily fueled by natural gas but can use Mazute, a heavy
oil, as an alternative fuel source if necessary. The heat
plant’s design permits the future addition of generators to
allow generation of electrical power from the plant’s excess
steam.
In October 1997, following a review
of the heat plant’s original design and the development of a
preliminary cost estimate for completion, Ukraine and the DOE
entered into an agreement to complete the plant. Work on the
plant had been halted in 1991 at 20 percent completion due to
insufficient Ukrainian funding.
The
United States and Ukraine provided $32.5 million and $7.5
million, respectively, to finish the project. Full scale
construction recommenced in 1998, and in April 2001 the
boiler-testing phase began with the successful ignition of
Boiler No. 4. Construction was completed in June. Testing by
the final Ukrainian State Acceptance Commission was scheduled
for fall of 2001, at which time US involvement in the project
ended.
“My time in Slavutych has been
challenging in many ways, but overall it has been very
rewarding,” said Jim Hartley, senior project manager with the
International Nuclear Safety Program (INSP), who has lived in
Slavutych, Ukraine for the past two years to oversee
construction of the $40 million heat plant project. “It has
been challenging integrating Western practices into a
Ukrainian managed project, but everyone has been dedicated to
keeping the project on track and staying on schedule and
within budget.”
In September, PNNL began aiding
Bechtel, Électricité de France, and Battelle, which manages
PNNL, to fulfill a $22 million contract to manage the Shelter
Implementation Plan (SIP). SIP is a project to enclose
Chornobyl Reactor Unit 4 in an environmentally secure
structure until the radiation level of fuel contained within
the reactor dissipates enough to permit safe removal and
storage.
PNNL offers regular support to the
National Nuclear Security Administration’s Office of
International Nuclear Safety and Cooperation. The office
conducts and participates in comprehensive, cooperative
efforts to reduce the risks from Soviet-designed nuclear
plants through correcting major safety deficiencies and
establishing safe, self-sustaining operational and
maintenance infrastructures. This work is done in cooperation
with other G-7 countries and international organizations.
|
_____________________________________________
Site last updated:
Thursday, February 22, 2007
Webmaster
|